With the recent high heat & humidity, work has slowed down a bit. But managed to get over to W7WZ’s new Fort Mill home & begin stacking his 45G tower. Slow going, as I’m putting 502s insulators in the EHS guy cables, at 13-foot intervals! Then, finding the first guy bracket installed incorrectly slowed things down, as John wanted me to make that right. Installing temporary EHS guys (with the multiple climbs), etc. slowed things down again. We’ve got three more sections to go, then it’s on to Tower Two, another 100-footer.
Next week Marti & I will be visiting her youngest son in Chicago. Hopefully it’ll be cooler there…
stay tuned